Location: Tandragee WWTW

Client: GEDA

Date: August 2018

Details: Replace steel sludge tanks with reinforced concrete at Tandragee WWTW
Working within a Live NI Water site, the ONCCE site team worked closely with the GEDA management to achieve a high quality product in the shortest possible time. Works involved installing dowels to the piled base where the steel tank had stood, forming a new base and forming circular walls with the Peri Rundflex system. The roof was pre-cast in an adjacent yard by ONCCE and installed by our on site team.